Neepsend Lane Gasworks

Customer:National Grid Property Holdings

Value: £10 million

VHE has carried out five phases of work on the former Neepsend Gasworks in Sheffield between 2006 and 2012 on behalf of National Grid Properties totalling in excess of £10 million.

The city centre site covers an area of approximately 5.3ha and was used for the manufacture of Town Gas from the 1880s until its decommissioning in 1967. Demolition of the remaining gas works structures was carried out in the early 1980’s whereupon the site was leased for the purposes of treatment and transfer of construction and demolition wastes. The site was finally abandoned around 1986 and returned to National Grid.

Remedial works undertaken by VHE included screening the overlying construction and demolition wastes, selective excavation, treatment and disposal of contaminated soils associated with the former gas works and groundwater treatment. The overlying construction and demolition materials were excavated and screened to remove waste materials such as paper, plastic, timber and metals in order to render them suitable for re-use as fill on the site. This recovery operation reduced the amount of construction and demolition waste removed from site to around 1.5% of the original tonnage.

In common with many former gas works sites, live plant was still present within the site and had to be considered during the design of the works. The principal hazard to be considered during the works was the presence of a live overhead 36” medium pressure gas main, which crossed the site from east to west. This gas main lay approximately 2.5m from the edge of two of the four 15m deep gas holders to be excavated and required significant temporary works measures to be in place to provide additional stability during the works.

Other hazards included a 7m high retaining wall forming the eastern boundary, which retained a live railway line and the presence of a civil engineering contractor who was a tenant on the southern section of the site. The eastern retaining wall had been constructed in the 1890s and had been buried during the 1980s. The condition of the wall was unknown and during the works a structural surveyor was appointed to carry out periodic surveys as sections were uncovered.

A total of 17,000 tonnes of contaminated material was sentenced for treatment by bioremediation. Primarily, bioremediation was used to reduce the classification of soils from hazardous to non-hazardous in order to minimise the amount of waste consigned to hazardous waste facilities. In addition, around 4000 tonnes was successfully treated for re-use on site.

Hydrocarbon contaminated groundwater was extracted during remediation and pumped to a water treatment area comprising 6 holding tanks and a treatment system. Treatment comprised a 3 stage oleophilic, hydrophobic wired unit feeding a carbon filter pod. All treated waters were discharged under a formal consent agreed with the local water authority.

Other projects

Safe Contractor
UVDB Registered
Chas
ISO 45001
ISO 14001
ISO 9001
  • Head Office
  • 6 Newton Business Centre
  • Chapeltown
  • Sheffield
  • S35 2PH
  • Tel: 01226 320150
  • Scotland Office
  • Antonine House
  • 5 Carradale Crescent
  • Broadwood Business Park
  • Cumbernauld
  • Scotland
  • G68 9LE
  • Tel: 01236 457157
  • North West Office
  • Ensphere House
  • Warrington Road
  • Risley
  • Croft
  • Warrington
  • WA3 6BH
  • Tel: 07771 868765

Follow Us

© 2024 Copyright VHE Construction plc

Registered Office: 3175 Century Way, Thorpe Park, Leeds, LS15 8ZB.
Registered in England no. 1457182. VHE Construction plc is a wholly owned subsidiary of Renew Holdings plc.