Stella Power Station comprised Northern and Southern sections, located on opposite sides of the River Tyne.

VHE was awarded the contract to decommission both. The Northern section was the largest, most heavily contaminated, and necessitated the most challenging dismantling operation.

The demolition of Stella North Power Station firstly required the removal of a significant amount of asbestos from the plant. A total of one hundred and first 30m³ skips of this material was disposed of in a licensed landfill site. Next, a number of structures were felled by means of controlled explosions, including the twin 115m high brick chimneys.

The contract produced 23,000 tonnes of scrap metal, which was processed for recycling at steelworks in Rotherham and Sheffield. All brick and concrete arisings from the demolition were crushed and stockpiled, to be used as hardcore in the future redevelopment of the reclaimed site.

Safe Contractor
UVDB Registered
Chas
ISO 45001
ISO 14001
ISO 9001
  • Head Office
  • 6 Newton Business Centre
  • Chapeltown
  • Sheffield
  • S35 2PH
  • Tel: 01226 320150
  • Scotland Office
  • Antonine House
  • 5 Carradale Crescent
  • Broadwood Business Park
  • Cumbernauld
  • Scotland
  • G68 9LE
  • Tel: 01236 457157
  • North West Office
  • Ensphere House
  • Warrington Road
  • Risley
  • Croft
  • Warrington
  • WA3 6BH
  • Tel: 07771 868765

Follow Us

© 2024 Copyright VHE Construction plc

Registered Office: 3175 Century Way, Thorpe Park, Leeds, LS15 8ZB.
Registered in England no. 1457182. VHE Construction plc is a wholly owned subsidiary of Renew Holdings plc.