Albion Landfill Site, Capping Works, Swadlincote

Customer:Veolia Environmental Services

Value: £77,000

After a previously successful contract to construct a new 1,000,000m³ capacity cell in the landfill at Albion, Swadlincote, VHE was appointed main contractor to carry out capping works to a completed cell.

The works included:

• Excavation and placement of 5,400m3 regulatory layer, 300mm thick, across the completed cell

• Excavation and placement of 18,000m3 1m thick clay cap to strict specification

• 14,700m3 colliery spoil was then placed as a lower restoration layer

• 6,300m3 subsoil and 6,000m3 of topsoil were placed in varying thicknesses prior to landscaping which included 15,000m2 seeding

• VHE also installed 320m of perforated HDPE leachate recirculation pipe to tie into the existing leachate system

• All the works were inspected by the CQA Engineer, as well as a visit by the Environment Agency Officer who deals with engineering works on landfills

Investors in Diversity
Safe Contractor
UVDB Registered
Chas
ISO 45001
ISO 14001
ISO 9001
  • Head Office
  • 6 Newton Business Centre
  • Chapeltown
  • Sheffield
  • S35 2PH
  • Tel: 01226 320150
  • Scotland Office
  • Antonine House
  • 5 Carradale Crescent
  • Broadwood Business Park
  • Cumbernauld
  • Scotland
  • G68 9LE
  • Tel: 01236 457157
  • North West Office
  • Ensphere House
  • Warrington Road
  • Risley
  • Croft
  • Warrington
  • WA3 6BH
  • Tel: 01226 320150

Follow Us

© 2024 Copyright VHE Construction plc

Registered Office: 3175 Century Way, Thorpe Park, Leeds, LS15 8ZB.
Registered in England no. 1457182. VHE Construction plc is a wholly owned subsidiary of Renew Holdings plc.