Peckfield Landfill Cell 7

Customer:Caird Bardon

Value: £0.7 million

This project involved the construction of a new 20,000m2 cell in the existing quarry and landfill at Peckfield on the outskirts of Leeds.

The works included:

  • Excavation of a 300m long, 3m deep groundwater drainage trench through solid rock formation
  • Cell construction comprising of two drainage and two sealing layers, and 4m high perimeter bunds to four sides
  • Installation of leachate detection sump and associated ductile iron pipework.
  • Installation of 2.5mm HDPE impermeable HDPE liner with welded seams, also tied in to the carefully exposed existing cell liner.
  • Placing of 300mm thick quarry fines protection layer to the HDPE liner on the cell floor, and 1m thick clay protection layer on the cell bunds.
  • Import of 350,000 car tyres, individually placed in a 3 layer chevron pattern to form a drainage layer.

VHE’s works involved the removal of materials from, and transportation through, both the existing landfill and quarry.

Safe Contractor
UVDB Registered
Chas
ISO 45001
ISO 14001
ISO 9001
  • Head Office
  • 6 Newton Business Centre
  • Chapeltown
  • Sheffield
  • S35 2PH
  • Tel: 01226 320150
  • Scotland Office
  • Antonine House
  • 5 Carradale Crescent
  • Broadwood Business Park
  • Cumbernauld
  • Scotland
  • G68 9LE
  • Tel: 01236 457157
  • North West Office
  • Ensphere House
  • Warrington Road
  • Risley
  • Croft
  • Warrington
  • WA3 6BH
  • Tel: 07771 868765

Follow Us

© 2024 Copyright VHE Construction plc

Registered Office: 3175 Century Way, Thorpe Park, Leeds, LS15 8ZB.
Registered in England no. 1457182. VHE Construction plc is a wholly owned subsidiary of Renew Holdings plc.