Customer:Harworth Group
Value: £6,338,319
VHE undertook reclamation / remediation and infrastructure works at the former Harworth Coking Works site South Yorkshire
VHE undertook works on two parts of the former Harworth Colliery site simultaneously. These were known as Harworth Coking Works (southern section) and Harworth Parcel 1 (northern section) with works being undertaken to create development platforms for sale to housing developers.
The Harworth Coking Works project involved:
The 7 Ha site was turned over to 2.5m with further excavation to 5m should contamination or foundations be present. Relic foundations were removed and reprocessed into 6F2 and Type 1 to be used in the earthworks platform and retained on site for use in the future development. Extensive hydrocarbon contamination was identified in soils across site with ex-situ bioremediation used to treat 5221m3 of contaminated soil. Upon completion of the bioremediation treated soils were validated to confirm compliance to site target levels and reused at depth within the soil platform.
Grossly contaminated soils that were unable to be treated on site were sent to offsite treatment centers or licensed landfill facilities. A 200mm low permeability cap was installed across the surface of the site following completion of the turnover for the purpose of reducing infiltration.
VHE completed the validation reports for the project for regulatory sign off.
Following the earthworks, infrastructure works was undertaken to serve the future housing developments.
The infrastructure works associated with the previously remediated Parcel 1 site were undertaken by VHE to enable the commencement of further development.
VHE constructed 0.5km of highway to adoptable standards under a Section 38 agreement, which was administered and overseen by Via EM on behalf of Nottinghamshire County Council. VHE also completed all the associated foul and storm water drainage installations to adoptable standards under Section 104 and Section 185 agreements with Severn Trent Water.
Key elements undertaken and completed include:
VHE faced challenges during the contract which saw us aid both the client and the designer to reach practical and viable solutions. These included locating existing HV cables where accurate historic plans did not exist, using vacuum excavation to enable the designer to finalise the position of the pumping station, the substation and drainage pipework alignments. In addition VHE met the challenge of coordinating and facilitating the works and requirements of the multiple utility companies to ensure timescales and key dates associated with the construction programme and the client’s contractual commitments to various house builders were met.
VHE continued to employ value engineering techniques and policy throughout the contract. Coal tar bound asphalt was temporarily stored on site which was associated with the remediation of the adjacent Coking Works. VHE proposed that this material could be cement stabilised and reused as sub-base material within a section of the permanent works, thus encapsulating any potential for contaminants to leach. This value engineering strategy made it a viable and cost effective product for re-use within the permanent works, prevented the material from being disposed of to landfill and reduced the import required to site.