Customer:Harworth Group
Value: £2 million
The construction of a new highway to access residential development plots on the former Harworth Coking Works site which VHE had previously remediated.
The award of this contract saw the continuation of the successful relationship between VHE Construction and Harworth Group. Following the completion of the remediation contracts to the Coking Works and Parcel 1 on the same site, VHE were awarded the infrastructure package that would ultimately serve the future housing developments on the plots associated with Parcel 1.
VHE constructed 0.5km of highway to adoptable standards under a Section 38 agreement, which was administered and overseen by Via EM on behalf of Nottinghamshire County Council. VHE also completed all the associated foul and storm water drainage installations to adoptable standards under Section 104 and Section 185 agreements with Severn Trent Water.
Key elements undertaken and completed include:
VHE faced challenges during the contract which saw us aid both the client and the designer to reach practical and viable solutions. These included locating existing HV cables where accurate historic plans did not exist, using vacuum excavation to enable the designer to finalise the position of the pumping station, the substation and drainage pipework alignments. In addition VHE met the challenge of coordinating and facilitating the works and requirements of the multiple utility companies to ensure timescales and key dates associated with the construction programme and the client’s contractual commitments to various house builders were met.
VHE continued to employ value engineering techniques and policy throughout the contract. Coal tar bound asphalt was temporarily stored on site which was associated with the remediation of the adjacent Coking Works. VHE proposed that this material could be cement stabilised and reused as sub-base material within a section of the permanent works, thus encapsulating any potential for contaminants to leach. This value engineering strategy made it a viable and cost effective product for re-use within the permanent works, prevented the material from being disposed of to landfill and reduced the import required to site.